Electrical installations at Frankfurt Airport, Flughafen Terminal 3 PH 606.

Frankfurt Airport, known as one of the busiest and most important airports in Europe, is currently the largest construction site on the continent. The new Terminal 3, which is under construction, covers an impressive area of 176,000 m², while the main terminal building itself covers 403,000 m². In addition, three bridges are planned for passenger boarding as part of this project.

Monting montaža is hired to perform specific electrical installation work, which includes:

  • Laying cables of various cross-sections and types,
  • Installation and connection of electrical cabinets,
  • Installation of lighting, fire alarm, and performance of necessary measurements,
  • Preparation of revision documentation.

Works on the implementation of the contracted electrical installations began in mid-2023. year, and completion is scheduled for the end of 2025. The new terminal is scheduled to be commissioned in 2026. Year.